Overview of the Project

The process for implementing a new JANET backbone can be broken down into three overall stages. This starts with a User Requirements Analysis, which leads, if necessary, and if funding is available, to a procurement stage. Once the procurement has been completed we then move to an implementations stage.

To date the procurement process for SuperJANET5 has completed and the rollout of the backbone infrastructure is currently underway.

  Activity Timescale
  Requirements Analysis 2H 2003
  Obtaining Funding Authorisation 1Q 2004
  Pre-procurement planning 1H 2004
  Initiate the backbone procurement 4Q 2004
Rollout of the SuperJANET5 backbone commences End 2005
  Close SuperJANET4 backbone 2H 2006
End of SuperJANET4 contracts with Thus for the SuperJANET backbone in Scotland and MCI for the rest of the UK. End 2006